CCR Rule Compliance Data and Information

On April 17, 2015, the Environmental Protection Agency (EPA) promulgated regulations regarding the management of Coal Combustion Residuals (CCR) generated by electrical utilities. This rule, effective October 19, 2015, established standards for the management and disposal of CCR by coal-fired power plants. The standards have been phased in over a multi-year period. EPA’s CCR regulations are applicable to the CCR management practices at Evergy’s Jeffrey Energy Center, Lawrence Energy Center, Tecumseh Energy Center (coal-fired power plant closed in 2018), La Cygne Generating Station, Iatan Generating Station, Sibley Generating Station (coal-fired power plant closed in 2018), and Montrose Generating Station (coal-fired power plant closed in 2018). These facilities are also regulated under Kansas and Missouri state laws, regulations, and permits.

In 2017 EvergyTM was formed as the product of a merger between Westar Energy, Inc and Great Plains Energy, Inc (parent company of Kansas City Power & Light Company and KCP&L Greater Missouri Operations Company). The facilities named as “energy centers” were previously Westar Energy facilities and those named as “generating stations” were previously Great Plains Energy facilities.

As part of the CCR Rule EPA finalized a requirement for owners and operators of CCR units to establish and maintain a publicly accessible Internet site of required CCR documents. CCR documents developed prior to October 2019 are identified according to the pre-merger company names; those developed during and after October 2019 identify using the Evergy brand name. Note that some documents are developed only once; others annually (typically retained for five years); and others are revised as needed for operational updates, to correct errors, etc. If revised, a table after the cover page of the latest document indicates the document revisions. Please direct any questions via email to EvergyCCR@evergy.com. All documents may be viewed by selecting the below drop-down filters. 

Document Title Company Station CCR Unit Document Type
TEC Bottom Ash Settling Area Post Closure Plan 10-17-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Closure and Post-closure Care
TEC Bottom Ash Settling Area Location Restrictions Demonstration Report 10-17-2018 Evergy Tecumseh Energy Center Bottom Ash Settling Area Location Restrictions
Tecumseh Energy Center Bottom Ash Settling Area Initiation of Closure Notice 10-09-2018 Evergy Tecumseh Energy Center Bottom Ash Settling Area Closure and Post-closure Care
TEC Bottom Ash Settling Area Closure Plan 10-14-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Closure and Post-closure Care
TEC 322 Landfill Post Closure Plan 10-14-2016 Evergy Tecumseh Energy Center 322 Landfill Closure and Post-closure Care
TEC 322 Landfill Location Restrictions Demonstration Report 10-17-2018 Evergy Tecumseh Energy Center 322 Landfill Location Restrictions
TEC 322 Landfill Closure Plan 10-14-2016 Evergy Tecumseh Energy Center 322 Landfill Closure and Post-closure Care
LEC Pond4 Post Closure Memo 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Closure and Post-closure Care
LEC Pond4 Location Restrictions 10-05-2016 Evergy Lawrence Energy Center Area 4 Pond Location Restrictions
LEC Pond4 Liner Design Report 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Design Criteria
LEC Pond4 Inactive Closure Notification 2018 Update 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Closure and Post-closure Care
LEC Pond4 Inactive Closure Notification 12-15-2015 Evergy Lawrence Energy Center Area 4 Pond Closure and Post-closure Care
Closure Plan 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Closure and Post-closure Care
Post-closure Plan Requirement 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Closure and Post-closure Care
Notification of Intent to Initiate Closure of Inactive CCR Surface Impoundment 12-10-2015 Evergy Lawrence Energy Center Area 3 Pond Closure and Post-closure Care
Liner Design Criteria Report 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Design Criteria
Closure Plan 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Closure and Post-closure Care
Updated Notification of Intent to Initiate Closure of an Inactive CCR Surface 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Closure and Post-closure Care
Liner Design Criteria Report 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Design Criteria
Post Closure Plan Requirement 04-17-2018 Evergy Lawrence Energy Center Area 2 Pond Closure and Post-closure Care
Location Restrictions Demonstrations for Units Impacted 10-05-2016 Evergy Lawrence Energy Center Area 2 Pond Location Restrictions
Closure Plan 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Closure and Post-closure Care
Location Restrictions Assessment 03-30-2018 Evergy Lawrence Energy Center 847 Landfill Location Restrictions
2017 Annual Groundwater Monitoring and Corrective Action Report 01-31-2018 Evergy Lawrence Energy Center 847 Landfill Groundwater Monitoring and Corrective Action
2018 Annual Groundwater Monitoring and Corrective Action Report 01-15-2019 Evergy Lawrence Energy Center 847 Landfill Groundwater Monitoring and Corrective Action
Closure Plan 03-30-2018 Evergy Lawrence Energy Center 847 Landfill Closure and Post-closure Care
Post Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Fly Ash Landfill Closure and Post-closure Care
Location Restrictions Demonstration Report 10-17-2018 Evergy Jeffrey Energy Center Fly Ash Landfill Location Restrictions
Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Fly Ash Landfill Closure and Post-closure Care
Post Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Closure and Post-closure Care
Location Restrictions Demonstration Report 10-17-2018 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Location Restrictions
Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Closure and Post-closure Care
Post Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Closure and Post-closure Care
Location Restrictions Demonstration Report Aquifer Separation 10-17-2018 Evergy Jeffrey Energy Center Bottom Ash Settling Area Location Restrictions
Location Restrictions Demonstration Report - Wetlands Fault Areas Sesimic Impact Zone 10-01-2018 Evergy Jeffrey Energy Center Bottom Ash Settling Area Location Restrictions
Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Closure and Post-closure Care
Post Closure Plan 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Closure and Post-closure Care
Location Restrictions 10-05-2016 Evergy Jeffrey Energy Center Bottom Ash Pond Location Restrictions
2018 Closure Notification Update 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Closure and Post-closure Care
Closure Plan 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Closure and Post-closure Care
Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Landfill Closure and Post-closure Care
Post Closure Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Landfill Closure and Post-closure Care
Location Restrictions Demonstration Report 10-17-2018 Evergy Jeffrey Energy Center Bottom Ash Landfill Location Restrictions
2017 Annual Groundwater Monitoring and Corrective Action Report 01-31-2018 Evergy Jeffrey Energy Center Bottom Ash Landfill Groundwater Monitoring and Corrective Action
JEC Groundwater Monitoring System Certification Rev 0 10-17-2017 Evergy Jeffrey Energy Center Site Wide Documents Unknown
Assessment Mon Program Notification Sept 2018 Sampling Event SSL 2-14-2019 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
JEC Groundwater Monitoring Systems Certification Rev 1 4-17-2019 Evergy Jeffrey Energy Center Site Wide Documents Unknown
JEC CCR Fugitive Dust Control Plan Revision 2 4-04-2018 Evergy Jeffrey Energy Center Site Wide Documents Unknown
La Cygne Upper AQC Imp Location Restriction Demo Report 10-17-18 Evergy La Cygne Generating Station Upper AQC Impoundment Location Restrictions
La Cygne Lower AQC Imp Loc Restriction Demo Report 10-17-18 Evergy La Cygne Generating Station Lower AQC Impoundment Location Restrictions
La Cygne Bottom Ash Imp Loc Restriction Demo Report 10-17-18 Evergy La Cygne Generating Station Bottom Ash Impoundment Location Restrictions
La Cygne Landfill Loc Restriction Demo Report 10-17-18 Evergy La Cygne Generating Station CCR Landfill Location Restrictions
La Cygne 2018 CCR Fugitive Dust Control Report 12-19-2018 Evergy La Cygne Generating Station All Facility CCR Units All Facility CCR Units
La Cygne Upper AQC Imp 2018 Annual Inspection Report 1-9-2019 Evergy La Cygne Generating Station Upper AQC Impoundment Operating Criteria
La Cygne Lower AQC Imp 2018 Annual Inspection Report 1-9-2019 Evergy La Cygne Generating Station Lower AQC Impoundment Operating Criteria
La Cygne CCR Landfill 2018 Annual Inspection Report 1-9-2019 Evergy La Cygne Generating Station CCR Landfill Operating Criteria
La Cygne UAQC 2018 GW Annual Report 1-30-2019 Evergy La Cygne Generating Station Upper AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne LF LAQC 2018 GW Annual Report 1-30-2019 Evergy La Cygne Generating Station Lower AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne LF LAQC 2018 GW Annual Report 1-30-2019 Evergy La Cygne Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
La Cygne Bottom Ash Imp 2018 GW Annual Report 1-30-2019 Evergy La Cygne Generating Station Bottom Ash Impoundment Groundwater Monitoring and Corrective Action
TEC 322 Landfill 2018 Annual Groundwater Report 01-31-2019 Evergy Tecumseh Energy Center 322 Landfill Unknown
TEC 322 Landfill 2017 Annual Inspection Report 01-12-2018 Evergy Tecumseh Energy Center 322 Landfill Unknown
TEC 322 Landfill 2016 Annual Inspection Report 01-16-2017 Evergy Tecumseh Energy Center 322 Landfill Unknown
TEC 322 Landfill 2015 Annual Inspection Report 01-15-2016 Evergy Tecumseh Energy Center 322 Landfill Unknown
TEC 322 Landfill 2017 Annual Groundwater Report 01-31-2018 Evergy Tecumseh Energy Center 322 Landfill Unknown
TEC 2017 Bottom Ash Settling Area Annual Inspection 01-12-2018 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC 2016 Bottom Ash Settling Area Annual Inspection 01-15-2017 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC 2018 Bottom Ash Settling Area Annual Inspection 01-11-2019 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC 2015 Bottom Ash Settling Area Annual Inspection 01-15-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
Montrose S Ash Imp Loc Restriction Demo Report-10-17-18 Evergy Montrose Generating Station South Ash Impoundment Location Restrictions
Montrose N Ash Imp Loc Restriction Demo Report 10-17-18 Evergy Montrose Generating Station North Ash Impoundment Location Restrictions
Montrose CCR Landfill Loc Restriction Demo Report 10-17-18 Evergy Montrose Generating Station CCR Landfill Location Restrictions
2018 Montrose CCR Landfill Annual Inspection Report 1-9-2019 Evergy Montrose Generating Station CCR Landfill Operating Criteria
Montrose CCR LF 2018 GW Annual Report 1-30-2019 Evergy Montrose Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Montrose N and S Ash Imp 2018 GW Annual Report 1-30-2019 Evergy Montrose Generating Station South Ash Impoundment Groundwater Monitoring and Corrective Action
Montrose N and S Ash Imp 2018 GW Annual Report 1-30-2019 Evergy Montrose Generating Station North Ash Impoundment Groundwater Monitoring and Corrective Action
Montrose 2018 CCR Fugitive Dust Control Report 12-19-2018 Evergy Montrose Generating Station All Facility CCR Units All Facility CCR Units
Iatan LF Loc Restriction Demo Report 10-17-18 Evergy Iatan Generating Station CCR Landfill Location Restrictions
Iatan 2018 CCR Fugitive Dust Control Report 12-19-2018 Evergy Iatan Generating Station All Facility CCR Units All Facility CCR Units
JEC 2018 Groundwater Monitoring Statistical Method Certification 1-15-2018 Evergy Jeffrey Energy Center Site Wide Documents Unknown
JEC 2017 Annual Fug Dust Report 12-12-2017 Evergy Jeffrey Energy Center Site Wide Documents Unknown
Iatan Dust Control Plan Rev 2 12-19-2018 Evergy Iatan Generating Station All Facility CCR Units All Facility CCR Units
JEC 2016 Annual Fug Dust Report 12-12-2016 Evergy Jeffrey Energy Center Site Wide Documents Unknown
2018 Iatan CCR Landfill Annual Inspection Report 1-9-2019 Evergy Iatan Generating Station CCR Landfill Operating Criteria
JEC Fly Ash Landfill 2017 Annual Inspection 1-12-2018 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
Iatan CCR LF 2018 GW Annual Report 1-30-2019 Evergy Iatan Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
JEC Fly Ash Landfill 2016 Annual Inspection 1-16-2017 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
JEC Fly Ash Landfill 2015 Annual Inspection 1-15-2016 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
Iatan Ash Imp Stat Method Certification 4-17-2019 Evergy Iatan Generating Station Ash Impoundment Groundwater Monitoring and Corrective Action
Iatan Ash Imp Groundwater Network Cert Rev 1-5-08-2019 Evergy Iatan Generating Station Ash Impoundment Groundwater Monitoring and Corrective Action
JEC Fly Ash Landfill 2019 Area 2 Landfill Design Certification 9-12-2019 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
Iatan Ash Imp Groundwater Network Cert Rev 0 4-16-2019 Evergy Iatan Generating Station Ash Impoundment Groundwater Monitoring and Corrective Action
JEC FGD Landfill 2018 Phase 1C Design Certification 9-10-2018 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
Iatan Ash Imp 2019 Groundwater Annual Report 7-31-19 Evergy Iatan Generating Station Ash Impoundment Groundwater Monitoring and Corrective Action
JEC FGD Landfill 2017 Annual Inspection 1-12-2018 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
JEC FGD Landfill 2015 Annual Inspection 1-15-2016 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
JEC FGD Landfill 2016 Annual Inspection 1-15-2017 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
JEC Bottom Ash Settling Area 2017 Annual Inspection 1-12-2018 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
JEC Bottom Ash Settling Area 2016 Annual Inspection 1-16-2017 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
JEC Bottom Ash Settling Area 2015 Annual Inspection 1-15-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Sibley CCR Landfill Restriction Demo Report 10-17-18 Evergy Sibley Generating Station CCR Landfill Location Restrictions
JEC Bottom Ash Settling Area 2018 Annual Inspection 1-11-19 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Sibley F Ash Imp Loc Restriction Demo Report 10-17-18 Evergy Sibley Generating Station Fly Ash Impoundment Location Restrictions
Sibley Slag Set Imp Loc Restriction Demo Report 10-17-18 Evergy Sibley Generating Station Slag Impoundment Location Restrictions
Sibley 2018 CCR Fugitive Dust Control Report 12-19-2018 Evergy Sibley Generating Station All Facility CCR Units All Facility CCR Units
2018 Sibley CCR Landfill Annual Inspection Report 1-9-2019 Evergy Sibley Generating Station CCR Landfill Operating Criteria
JEC Bottom Ash Pond 2017 Annual Inspection 7-17-2017 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
JEC Bottom Ash Pond 2019 Annual Groundwater Report 7-31-2019 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
2018 Sibley Fly Ash Imp Annual Inspection Report 1-9-2019 Evergy Sibley Generating Station Fly Ash Impoundment Groundwater Monitoring and Corrective Action
TEC 2017 Annual Fugitive Dust Report 12-12-2017 Evergy Tecumseh Energy Center Site Wide Documents Unknown
TEC 2016 Annual Fugitive Dust Report 12-12-2016 Evergy Tecumseh Energy Center Site Wide Documents Unknown
Sibley Landfill 2017 GW Annual Report 1-30-2018 Rev1 Evergy Sibley Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
TEC Groundwater Monitoring Statistical Method Certification 10-17-2017 Evergy Tecumseh Energy Center Site Wide Documents Unknown
Sibley Landfill 2018 Groundwater Annual Report 1-30-2019 Evergy Sibley Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
JEC Bottom Ash Landfill 2017 Annual Inspection 01-12-2018 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
JEC Bottom Ash Landfill 2016 Annual Inspection 01-16-2017 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
JEC Bottom Ash Landfill 2015 Annual Inspection 01-15-2016 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
Sibley Fly Ash Imp 2018 Groundwater Annual Report 1-30-2019 Evergy Sibley Generating Station Fly Ash Impoundment Groundwater Monitoring and Corrective Action
Sibley Slag Imp 2018 Groundwater Annual-Report 1-30-2019 Evergy Sibley Generating Station Slag Impoundment Groundwater Monitoring and Corrective Action
LEC 847 Landfil 2015 Annual Inspection 1-15-2016 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Landfill 2017 Annual Inspection 1-12-2018 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Landfill 2016 Annual InspectionI 1-16-2017 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Landfill Post Closure Plan Rev 0 10-14-2016 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Landfill Closure Plan Rev 0 10-14-2016 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Run On And Run Off Control System Plan Rev 0 10-14-2016 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Run On And Run Off Control System Plan Rev 1 3-30-2018 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC 847 Post-Closure Plan Rev 1 3-30-2018 Evergy Lawrence Energy Center 847 Landfill Unknown
LEC Pond 2 3 4 2017 Annual Inspection 7-17-2017 Evergy Lawrence Energy Center Area 4 Pond Unknown
LEC Pond 2 3 4 2017 Annual Inspection 7-17-2017 Evergy Lawrence Energy Center Area 3 Pond Unknown
LEC Pond 2 3 4 2017 Annual Inspection 7-17-2017 Evergy Lawrence Energy Center Area 2 Pond Unknown
LEC 2017 Annual Fugitive Dust Control Report 12-12-2017 Evergy Lawrence Energy Center Site Wide Documents Unknown
LEC 2016 Annual Fugitive Dust Control Report 12-12-2016 Evergy Lawrence Energy Center Site Wide Documents Unknown
LEC Ponds 2 3 4 2019 Annual Groundwater Report 7-31-2019 Evergy Lawrence Energy Center Area 4 Pond Unknown
LEC Ponds 2 3 4 2019 Annual Groundwater Report 7-31-2019 Evergy Lawrence Energy Center Area 3 Pond Unknown
LEC Ponds 2 3 4 2019 Annual Groundwater Report 7-31-2019 Evergy Lawrence Energy Center Area 2 Pond Unknown
LEC GW Monitoring-System-Certification Rev-1 4-17-2019 Evergy Lawrence Energy Center Site Wide Documents Unknown
LEC Statistical Method Certification Rev-1 4-17-2019 Evergy Lawrence Energy Center Site Wide Documents Unknown
La Cygne Upper AQC Imp IDF Control Plan 10-13-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Operating Criteria
La Cygne Upper AQC Imp 2016 Annual CCR Inspection Report 01-06-2017 Evergy La Cygne Generating Station Upper AQC Impoundment Operating Criteria
La Cygne Annual CCR 2015 Inspection Report UpperAQC Evergy La Cygne Generating Station Upper AQC Impoundment Operating Criteria
2017 La Cygne Upper AQC Imp Annual Inspection Report 01-09-18 Evergy La Cygne Generating Station Upper AQC Impoundment Operating Criteria
La Cygne UAQC StatMethod Cert 10-11-2017 Evergy La Cygne Generating Station Upper AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne UAQC GW Mon Sys Cert 10-11-2017 Evergy La Cygne Generating Station Upper AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne Upper AQC 2017 GW Annual Report 1-30-2018 Evergy La Cygne Generating Station Upper AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne Upper AQC Imp Structural Stability Report 10-11-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Design Criteria
La Cygne Upper AQC Imp Safety Factor Report 10-11-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Design Criteria
La Cygne Upper AQC Imp History of Construction Report 10-6-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Design Criteria
La Cygne Upper AQC Imp Hazard Potential Report 10-7-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Design Criteria
La Cygne Upper AQC Imp Post Closure Plan 10-13-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Closure and Post-closure Care
La Cygne Upper AQC Im Closure Plan 10-14-2016 Evergy La Cygne Generating Station Upper AQC Impoundment Closure and Post-closure Care
La Cygne Lower AQC Imp IDF Control Plan 10-13-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Operating Criteria
La Cygne Lower AQC Imp 2016 Annual CCR Inspection Report 01-06-2017 Evergy La Cygne Generating Station Lower AQC Impoundment Operating Criteria
2015 La Cygne Annual CCR Inspection Report LowerAQC Evergy La Cygne Generating Station Lower AQC Impoundment Operating Criteria
2017 La Cygne Lower AQC Imp Annual Inspection Report 01-09-18 Evergy La Cygne Generating Station Lower AQC Impoundment Operating Criteria
La Cygne LF LAQC Stat Cert 10-11-2017 Evergy La Cygne Generating Station Lower AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne LF-LAQC 2017 GW Annual Report 1-30-2018 Evergy La Cygne Generating Station Lower AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne LF LAQC GW Mon Sys-Cert 10-11-2017 Evergy La Cygne Generating Station Lower AQC Impoundment Groundwater Monitoring and Corrective Action
La Cygne Lower AQC Imp Structural Stability Report 10-11-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Design Criteria
La Cygne Lower AQC Imp Safety Factor Report 10-11-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Design Criteria
La Cygne Lower AQC Imp History of Construction Report 10-6-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Design Criteria
La Cygne Lower AQC Imp Hazard Potential Report 10-7-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Design Criteria
La Cygne Lower AQC Imp Post Closure Plan 10-13-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Closure and Post-closure Care
La Cygne Lower AQC Imp Closure Plan 10-14-2016 Evergy La Cygne Generating Station Lower AQC Impoundment Closure and Post-closure Care
La Cygne Landfill 2016 Annual CCR Inspection Report 01-06-2017 Evergy La Cygne Generating Station CCR Landfill Operating Criteria
La Cygne CCR Landfill Run On Run Off Control Plan 10-17-2016 Evergy La Cygne Generating Station CCR Landfill Operating Criteria
2015 La Cygne Annual CCR Inspection Report Landfill Evergy La Cygne Generating Station CCR Landfill Operating Criteria
2017 La Cygne CCR Landfill Annual Inspection Report 01-09-18 Evergy La Cygne Generating Station CCR Landfill Operating Criteria
La Cygne LF LAQC Stat Cert 10-11-2017 Evergy La Cygne Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
La Cygne LF LAQC GW Mon Sys Cert 10-11-2017 Evergy La Cygne Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
La Cygne LF LAQC 2017 GW Annual Report 1-30-2018 Evergy La Cygne Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
La Cygne Landfill Post Closure Plan 10-13-2016 Evergy La Cygne Generating Station CCR Landfill Closure and Post-closure Care
La Cygne Landfill Closure Plan 10-14-2016 Evergy La Cygne Generating Station CCR Landfill Closure and Post-closure Care
La Cygne Bottom Ash Imp IDF Control Plan 10-13-2016 Evergy La Cygne Generating Station Bottom Ash Impoundment Operating Criteria
La Cygne BotAsh StatMethod Cert 10-11-2017 Evergy La Cygne Generating Station Bottom Ash Impoundment Groundwater Monitoring and Corrective Action
La Cygne Bash GW Mon Sys Cert 10-11-2017 Evergy La Cygne Generating Station Bottom Ash Impoundment Groundwater Monitoring and Corrective Action
La Cygne Bot Ash Imp 2017 GW Annual Report 1-30-2018 Evergy La Cygne Generating Station Bottom Ash Impoundment Groundwater Monitoring and Corrective Action
La Cygne Bot Ash Imp Closure Plan 10-14-2016 Evergy La Cygne Generating Station Bottom Ash Impoundment Closure and Post-closure Care
La Cygne CCR Fugitive Dust Control Report 2016 12-19-16 Evergy La Cygne Generating Station All Facility CCR Units All Facility CCR Units
La Cygne 2017 CCR Fugitive Dust Control Report Final 12-19-2017 Evergy La Cygne Generating Station All Facility CCR Units All Facility CCR Units
TEC Bottom Ash Settling Area Structural Stability Assessment 10-03-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
La Cygne Dust Control Plan Rev One 5-3-2017 Evergy La Cygne Generating Station All Facility CCR Units All Facility CCR Units
TEC Bottom Ash Settling Area Safety Factor Assessment 10-03-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
Iatan Landfill Run On Run Off Control Sys Plan 10-17-2016 Evergy Iatan Generating Station CCR Landfill Operating Criteria
Iatan Landfill 2016 Annual CCR Inspection Report 01-06-2017 Evergy Iatan Generating Station CCR Landfill Operating Criteria
2015 Iatan Annual CCR Inspection Report Landfill Evergy Iatan Generating Station CCR Landfill Operating Criteria
2017 Iatan CCR Landfill Annual Inspection Report 01-09-18 Evergy Iatan Generating Station CCR Landfill Operating Criteria
Iatan Landfill StatMethod Cert 10-12-2017 Evergy Iatan Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Iatan Landfill GW MonSys Cert 10-12-2017 Evergy Iatan Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Iatan CCR LF 2017 GW Annual Report 1-30-18 Rev1 Evergy Iatan Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Iatan Landfill Closure Plan 10-14-2016 Evergy Iatan Generating Station CCR Landfill Closure and Post-closure Care
Iatan Landfill Post Closure Plan 10-13-2016 Evergy Iatan Generating Station CCR Landfill Closure and Post-closure Care
Iatan Ash Imp IDF Control Plan 4-16-2018 Evergy Iatan Generating Station Ash Impoundment Operating Criteria
Iatan Station Notification of Intent to Close Final Evergy Iatan Generating Station Ash Impoundment Closure and Post-closure Care
Iatan Ash Imp Closure Plan 4-16-2018 Evergy Iatan Generating Station Ash Impoundment Closure and Post-closure Care
Iatan CCR Fugitive Dust Control Report 12-19-2016 Evergy Iatan Generating Station All Facility CCR Units All Facility CCR Units
Iatan 2017 CCR Fugitive Dust Control Report 12-19-2017 Evergy Iatan Generating Station All Facility CCR Units All Facility CCR Units
Iatan Dust Control Plan Final Rev One 4-18-2017 Evergy Iatan Generating Station All Facility CCR Units All Facility CCR Units
TEC Bottom Ash Settling Area Liner Documentation 10-04-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC Bottom Ash Settling Area Hydrologic Hydraulic Capacity 10-14-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC Bottom Ash Settling Area History of Construction 10-05-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC Bottom Ash Settling Area Hazard Potential Classification 10-03-2016 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
TEC Bottom Ash Settling Area Emergency Action Plan 04-17-2017 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
Montrose S Fly Ash Imp IDF Control Plan 10-13-2016 Evergy Montrose Generating Station South Ash Impoundment Operating Criteria
Montrose N and S Ash Imp 2017 GW Annual Report 1-30-2018 Evergy Montrose Generating Station South Ash Impoundment Groundwater Monitoring and Corrective Action
TEC BASA September 2018 SSL Notification 02-14-2019 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
MontNS Ash StatMethod Cert 10-12-2017 Evergy Montrose Generating Station South Ash Impoundment Groundwater Monitoring and Corrective Action
MontNS Ash GWMonSys Cert 10-12-2017 Evergy Montrose Generating Station South Ash Impoundment Groundwater Monitoring and Corrective Action
Closure Plan Montrose South Ash Imp Final 10-14-16 Evergy Montrose Generating Station South Ash Impoundment Closure and Post-closure Care
Montrose N Fly Ash Imp IDF Control Plan 10-13-2016 Evergy Montrose Generating Station North Ash Impoundment Operating Criteria
Montrose N and S Ash Imp 2017 GW Annual Report 1-30-2018 Evergy Montrose Generating Station North Ash Impoundment Groundwater Monitoring and Corrective Action
MontNS Ash StatMethod Cert 10-12-2017 Evergy Montrose Generating Station North Ash Impoundment Groundwater Monitoring and Corrective Action
MontNS Ash GWMonSys Cert 10-12-2017 Evergy Montrose Generating Station North Ash Impoundment Groundwater Monitoring and Corrective Action
Montrose Landfill Run On Run Off Control Sys Plan 10-17-2016 Evergy Montrose Generating Station CCR Landfill Operating Criteria
TEC 2018 Annual Groundwater Report Bottom Ash Settling Area 01-31-2019 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
Montrose Landfill 2016 Annual CCR Inspection Report 01-06-2017 Evergy Montrose Generating Station CCR Landfill Operating Criteria
2015 Montrose Annual CCR Inspection Report Landfill Evergy Montrose Generating Station CCR Landfill Operating Criteria
TEC 2017 Annual Groundwater Report Bottom Ash Settling Area 01-31-2018 Evergy Tecumseh Energy Center Bottom Ash Settling Area Unknown
2017 Montrose CCR Landfill Annual Inspection Report 01-09-18 Evergy Montrose Generating Station CCR Landfill Operating Criteria
TEC 322 Landfill Run On Run Off Control Plan 10-14-2016 Evergy Tecumseh Energy Center 322 Landfill Unknown
Montrose CCR LF 2017 GW Annual Report 1-30-2018 Evergy Montrose Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Mont LF GW Mon Sys Cert 10-12-2017 Evergy Montrose Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Mont Landfill StatMethod Cert 10-12-2017 Evergy Montrose Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Montrose Landfill Post Closure Plan 10-13-2016 Evergy Montrose Generating Station CCR Landfill Closure and Post-closure Care
Montrose Landfill Closure Plan 10-14-2016 Evergy Montrose Generating Station CCR Landfill Closure and Post-closure Care
Montrose CCR Fugitive Dust Control Report 12-19-2016 Evergy Montrose Generating Station All Facility CCR Units All Facility CCR Units
TEC 322 Landfill 2018 Annual Inspection Report 01-11-2019 Evergy Tecumseh Energy Center 322 Landfill Unknown
Montrose 2017 CCR Fugitive Dust Control Report-Final 12-19-2017 Evergy Montrose Generating Station All Facility CCR Units All Facility CCR Units
TEC Groundwater Monitoring System Certification 10-17-2017 Evergy Tecumseh Energy Center Site Wide Documents Unknown
TEC Groundwater Monitoring Statistical Method Certification 01-15-2018 Evergy Tecumseh Energy Center Site Wide Documents Unknown
TEC Fugitive Dust Control Plan 10-15-2015 Evergy Tecumseh Energy Center Site Wide Documents Unknown
TEC 2018 Annual Fug Dust Report 12-12-2018 Evergy Tecumseh Energy Center Site Wide Documents Unknown
Assessment Monitoring Notification 08-15-2018 Evergy Tecumseh Energy Center Site Wide Documents Unknown
LEC Pond4 Structural Stability Assessment 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
LEC Pond4 Safety Factor Assesment 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
Hydrologic Hydraulic Capacity Plan 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
JEC 2018 Annual Fug Dust Report 12-12-2018 Evergy Jeffrey Energy Center Site Wide Documents Unknown
2017 Annual Groundwater Monitoring and Corrective Action Report 01-31-2018 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Sibley CCR Fugitive Dust Control Report 12-19-2016 Evergy Sibley Generating Station All Facility CCR Units All Facility CCR Units
Sibley 2017 CCR Fugitive Dust Control Report Final 12-19-2017 Evergy Sibley Generating Station All Facility CCR Units All Facility CCR Units
History of Construction 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
Hazard Potential Classification Assessment 04-18-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
2018 Annual CCR Inspection 07-13-2018 Evergy Lawrence Energy Center Area 4 Pond Unknown
Location Restriction Demonstrations for Units Impacted 10-05-2016 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Landfill Run On Run Off Control Sys Plan 10-17-2016 Evergy Sibley Generating Station CCR Landfill Operating Criteria
Initial Safety Factor Assessment 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Landfill Annual CCR Inspection Report 1-06-2017 Evergy Sibley Generating Station CCR Landfill Operating Criteria
Sibley Annual CCR Inspection Report Landfill 2015 Evergy Sibley Generating Station CCR Landfill Operating Criteria
Structural Stability Assessment 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley CCR Landfill Annual CCR Inspection Report 01-09-18 Evergy Sibley Generating Station CCR Landfill Operating Criteria
Sibley Landfill StatMethod Cert 10-12-2017 Evergy Sibley Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Sibley Landfill GW Mon Sys Cert 10-12-2017 Evergy Sibley Generating Station CCR Landfill Groundwater Monitoring and Corrective Action
Sibley Landfill Post Closure Plan 10-13-2016 Evergy Sibley Generating Station CCR Landfill Closure and Post-closure Care
Sibley Landfill Closure Plan 10-14-2016 Evergy Sibley Generating Station CCR Landfill Closure and Post-closure Care
Sibley Fly Ash Imp Structural Stability Report 10-11-2016 Evergy Sibley Generating Station Fly Ash Impoundment Design Criteria
Updated Notification of Intent to Initiate Closure of Inactive CCR Surface 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Fly Ash Imp Safety Factor Report 10-11-2016 Evergy Sibley Generating Station Fly Ash Impoundment Design Criteria
Sibley Fly Ash Imp History of Construction Report 10-6-2016 Evergy Sibley Generating Station Fly Ash Impoundment Design Criteria
Inflow Design Flood Control System Plan 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Fly Ash Imp Hazard Potential Report 10-7-2016 Evergy Sibley Generating Station Fly Ash Impoundment Design Criteria
Sibley Fly Ash Imp Closure Plan 10-14-2016 Evergy Sibley Generating Station Fly Ash Impoundment Closure and Post-closure Care
History of Construction 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Slag Imp Closure Plan 10-1-2016 Evergy Sibley Generating Station Slag Impoundment Closure and Post-closure Care
Sibley Slag Imp 2017 GW Annual Report 1-30-2018 Evergy Sibley Generating Station Slag Impoundment Groundwater Monitoring and Corrective Action
Hazard Potential Classification Assessment 04-18-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Sibley Slag Imp GW MonSys Cert 10-12-2017 Evergy Sibley Generating Station Slag Impoundment Groundwater Monitoring and Corrective Action
Sibley SlagImp StatMethod Cert 10-12-2017 Evergy Sibley Generating Station Slag Impoundment Groundwater Monitoring and Corrective Action
Sibley Slag Settling Imp IDF Control Plan 10-13-2016 Evergy Sibley Generating Station Slag Impoundment Operating Criteria
2018 Annual CCR Inspection 05-15-2018 Evergy Lawrence Energy Center Area 3 Pond Unknown
Structural Stability Assessment 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
Initial Safety Factor Assessment 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
Notification of Intent to Initiate Closure of an Inactive CCR Surface Impoundment 12-15-2015 Evergy Lawrence Energy Center Area 2 Pond Unknown
Inflow Design Flood Control System Plan 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
History of Construction 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
Hazard Potential Classification Assessment 04-18-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
2018 Annual CCR Inspection 05-15-2018 Evergy Lawrence Energy Center Area 2 Pond Unknown
2018 Annual CCR Inspection 11-27-2019 Evergy Lawrence Energy Center 847 Landfill Unknown
Groundwater Monitoring System Certification Existing - 10-17-2017 Evergy Lawrence Energy Center Site Wide Documents Unknown
Certification of Statistical Methods - 01-15-2018 Evergy Lawrence Energy Center Site Wide Documents Unknown
CCR Fugitive Dust Control Plan - Rev2 04-04-2018 Evergy Lawrence Energy Center Site Wide Documents Unknown
Annual CCR Fugitive Dust Control Report 12-10-2018 Evergy Lawrence Energy Center Site Wide Documents Unknown
Run On and Run Off Control System Plan 10-14-2016 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
2018 Annual CCR Inspection 11-28-2018 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
2018 Annual Groundwater Monitoring and Corrective Action Report 01-31-2019 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
2017 Annual Groundwater Monitoring and Corrective Action Report 01-31-2018 Evergy Jeffrey Energy Center Fly Ash Landfill Unknown
Run On Run Off Control System Plan 10-14-2016 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
2018 Annual CCR Inspection 11-28-2018 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
2018 Annual Groundwater Monitoring and Corrective Action Report 01-01-2019 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
2017 Annual Groundwater Report and Corrective Action Report 01-31-2018 Evergy Jeffrey Energy Center Flue Gas Desulfurization Landfill Unknown
Structural Stability Assessment 10-03-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Safety Factor Assessment 10-03-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Liner Documentation 10-04-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Inflow Design Flood Control System Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
History of Construction 10-05-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Initial Hazard Potential Classification Assessment 09-30-2016 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
2018 Annual Groundwater Monitoring and Corrective Action Report 01-31-2019 Evergy Jeffrey Energy Center Bottom Ash Settling Area Unknown
Structual Stability Assessment 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
Safety Factor Assessment 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
Liner Design Report 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
Hydrologic Hydraulic Capacity Plan 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
History of Construction 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
Hazard Potential 04-18-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
Notification of Intent to Initiate Closure 12-15-2015 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
2018 Annual CCR Inspection 07-13-2018 Evergy Jeffrey Energy Center Bottom Ash Pond Unknown
2018 Annual Groundwater Monitoring and Corrective Action Report 01-31-2019 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
Run On Run Off Control Plan 10-14-2016 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
2018 Annual CCR Inspection 11-28-2018 Evergy Jeffrey Energy Center Bottom Ash Landfill Unknown
Certification of Statistical Methods Revised 04-17-2019 Evergy Jeffrey Energy Center Site Wide Documents Unknown
Assessment Monitoring Notification 08-15-2018 Evergy Jeffrey Energy Center Site Wide Documents Unknown
Sibley Fly Ash Imp 2017 GW Annual Report 1-30-2018 Evergy Sibley Generating Station Fly Ash Impoundment Groundwater Monitoring and Corrective Action
Sibley-FlyAsh-Imp-GW-MonSys-Cert-10-12-2017 Evergy Sibley Generating Station Fly Ash Impoundment Groundwater Monitoring and Corrective Action
Sibley-FlyAshImp-StatMethod-Cert--10-12-2017 Evergy Sibley Generating Station Fly Ash Impoundment Groundwater Monitoring and Corrective Action
2017-Sibley-Fly-Ash-Imp-Annual-CCR-Inspection-Report-01-09-18 Evergy Sibley Generating Station Fly Ash Impoundment Operating Criteria
Sibley Fly Ash Imp 2016 Annual CCR Inspection Report_01-06-2017 Evergy Sibley Generating Station Fly Ash Impoundment Operating Criteria
SibleyAnnualCCRInspectionReport_FlyAsh_2015 Evergy Sibley Generating Station Fly Ash Impoundment Operating Criteria
Sibley-Fly-Ash-Imp-IDF-Control-Plan-10-13-2016 Evergy Sibley Generating Station Fly Ash Impoundment Operating Criteria
Sibley Dust Control Plan 10-19-2015 Evergy Sibley Generating Station All Facility CCR Units All Facility CCR Units
Montrose Dust Control Plan 10-08-2015 Evergy Montrose Generating Station All Facility CCR Units All Facility CCR Units
Closure-Plan-Montrose-North-Ash-Imp-Final-Rev_0-10-14-16 Evergy Montrose Generating Station North Ash Impoundment Closure and Post-closure Care